Sterling Fire Protection
Defence and Security Fire Protection
High-Security Installations

Defence and Security Fire Protection

Detention buildings and secured government or defence sites run on locks, screening and controlled access. This page covers the fire protection conflicts that creates and what Sterling can design, install and service.

Detention occupancy
Group B, Division 1
Emergency lighting duration
1 hour in Group B buildings
Fire alarm standard
CAN/ULC-S524:2019
Integrated systems testing
CAN/ULC-S1001:2011

Secure buildings turn the usual fire assumptions upside down

In most buildings the fire strategy starts with getting people out. In a detention facility the people can't leave on their own, and the doors that keep them in are the same doors the fire code cares about most. Everything else on a secure project follows from that tension.

Two things get lumped together here, and they should be kept apart. Detention buildings are a code category. The National Building Code puts jails, prisons and police stations with detention in Group B, Division 1. Secured sites of other kinds, such as defence or government property, are an access problem, not an occupancy group. They may be offices, labs or stores that happen to sit behind a fence. Their fire protection is ordinary. Getting onto the site to test it isn't.

Who decides the rules on a secure site

Start with who the authority is. For most Alberta buildings the AHJ is the municipality or accredited agency under the Safety Codes Act, and the fire code (NFC(AE) 2023, in force since May 1, 2024) applies as usual. Property owned or run by the federal government or a defence department may answer to a different authority. We haven't confirmed which fire rules govern any particular federal site, so ask the owner on day one, and get the design criteria in writing before drawings start.

Corrections operators and security owners also carry standards of their own. Those can go beyond the code. They can't go below it.

Locks that have to release in a fire

A locked cell door is a security device and a life-safety device at once. The National Building Code sets specific rules for these locks. An egress door serving a contained use area or impeded egress zone may be locked, provided it can be released locally with a key from both sides or remotely from controls readily available to security staff, and electrically operated locks have to run on emergency power and allow manual release by security staff (NBC(AE) 2023, 3.3.1.13). The release logic gets agreed between the AHJ, the operator and the hardware supplier before anyone programs a panel. It's a life-safety decision. It isn't a supplier's default.

The failures happen at the seams. The alarm panel, the door controller and the access control system can each be a different vendor's product, and a relay that's wired but never tested looks perfectly fine until the day it matters. Alberta references CAN/ULC-S1001:2011 for integrated systems testing (NFC(AE) 6.8.1.1 and NBC(AE) 3.2.9.1), which is precisely the test of whether alarms, door release, fans and the rest respond together. Ask whether your project's code path triggers it, and book the day early because it takes many hands.

Sprinkler heads made for people who'll try to defeat them

Ordinary pendent heads don't belong in a cell. Institutional heads are flush-mounted and tamper-resistant, and many add locking escutcheons or parts designed to break away under load. They're built for correctional and mental-health occupancies. Viking's published VK426 and VK427 heads are one example: K5.6, quick response, 175 psi maximum, pendent and horizontal sidewall, listed for light and ordinary hazard.

The catch is the listing. Light and ordinary hazard suits cells and corridors. It doesn't automatically cover a workshop, laundry or storeroom with a heavier fuel load in the same building. The designer sorts the areas by hazard class first and picks heads second. That's sprinkler system design at its plainest, and it's why fire protection design needs the finished ceiling details early.

Emergency lighting is a simpler item. In Group B buildings the code calls for one hour of duration (NBC(AE) 2023, 3.2.7.4). Emergency lighting testing in Alberta explains the monthly and yearly tests.

Smoke, compartments and the plan when nobody can leave

Detainees can't simply walk out, so designs usually lean on the building itself: compartments, sprinklers, smoke management and staffed procedures. Those are architectural and mechanical calls made in the code analysis, and they vary a lot from one building to the next. We're not going to pretend a webpage settles them.

What the fire protection contractor owns is the interface. The sprinkler flow switch, the alarm zones and any smoke control equipment have to behave exactly as the code analysis says. If an AHJ order or a design conflict comes up, a fire code consulting review of the occupancy classification is the usual first step.

Testing where you can't simply walk in

An annual fire alarm test under CAN/ULC-S536:2019 touches every device, and the sprinkler inspection touches every control valve. In a secure building, some of those are inside occupied cells or behind checkpoints. Plan the visit like a shutdown. Our impairment checklist covers how to run that shutdown.

  • Agree the date, the escorts and the areas that can't be cleared.
  • Ask what happens to a device you can't reach that day, and get it in writing.
  • Put monitoring on test and tell the operator before the first horn sounds, because a test alarm in a detention block is a real event for the people in it.
  • Arrange a fire watch plan before any planned impairment. An alarm out for more than 2 hours means notifying the fire department and, when directed, keeping continuous surveillance in the building (NFC(AE) Division C, 2.2.7.2). In a building nobody can evacuate, that surveillance is real staff hours.

Screening, badging, tool control and lockdown windows are set by the facility. Raise them at the first meeting, so the schedule is built around them instead of colliding with them.

What to settle before design starts

  1. Who the AHJ is, and whether a federal or operator authority sits above or beside them.
  2. How, when and by whom the door locks release on an alarm, and how that gets tested.
  3. Which areas are cells or secure rooms and which are ordinary, so heads and devices are chosen by hazard class.
  4. Ceiling finishes and access panels, so concealed or flush devices can still be reached and tested.
  5. Access rules for the crew, including escorts, ID and prohibited items.
  6. The shutdown plan for any impairment, including who staffs the fire watch.

What Sterling can do for a secure facility

We can design sprinkler and alarm layouts (hydraulic calculations, AutoCAD and HydraCAD drawings, BIM coordination with the security trades), install them as new work or as retrofits, run the annual inspection and testing, and handle a deficiency report or emergency call at any hour. Code questions about occupancy classification, or an order from the AHJ, go to our fire code consulting service. To start, call 780.760.0806 or use the contact page.

Frequently asked questions

Is every police station a detention occupancy?

No. The code's examples of Group B, Division 1 are jails, prisons and police stations with detention. A station that holds people in cells is classed that way, though the code lets a one-storey station of up to 600 m2 with detention quarters be classed as Group B, Division 2 instead (NBC(AE) 2023, 3.1.2.4). One without detention is more likely an ordinary building. The designer and the AHJ decide, so confirm the classification before you price the sprinklers.

Do federal and defence buildings follow the Alberta Fire Code?

It depends on who owns and administers the site, and we haven't verified the rule for any specific property. Provincial safety codes may not be the whole story on federal land. Ask the owner which authority applies before design begins.

Do fire alarms unlock detention doors automatically?

Not by default. The National Building Code lets egress doors in contained use areas and impeded egress zones stay locked, provided security staff can release them locally with a key or remotely from a control point, and electrically operated locks run on emergency power with a manual release (NBC(AE) 2023, 3.3.1.13). Whether any release is tied to the alarm is agreed between the AHJ, the operator and the designer. Then it gets tested together, not just device by device.

Sources

Have a secure building to protect or maintain?

Tell us the occupancy, who controls access and what the AHJ has said so far. We'll help you sort the fire protection work from the security constraints.